RENDERING SUPPORT SERVICES FOR THE SMOLENSKAYA CHP PLANT NO. 2 TURBINE UNIT NO. 3 UPGRADE PROJECT, PLANNED AS PART OF THE RUSSIA-WIDE DPM HEAT PLANTS MODERNIZATION PROGRAM
The Smolenskaya combined heat-and-power plant no. 2 is located in the town of Smolensk and is run by a company owned by the Quadra PJSC.
It delivers heat and electricity to the town of Smolensk.
Rated electric power output: 275 MW.
Rated heat output: 774 Gcal/h
EF-TEK is now providing support services for this plant´s Turbine unit No. 3 upgrade project. The scope of these services is as follows:
It delivers heat and electricity to the town of Smolensk.
Rated electric power output: 275 MW.
Rated heat output: 774 Gcal/h
EF-TEK is now providing support services for this plant´s Turbine unit No. 3 upgrade project. The scope of these services is as follows:
- providing support during the Turbine unit no. 3 main building foundation survey;
- participation in the long-lead equipment (turbine and generator) supply contract draft preparation; turbine and generator ToR drafting;
- participation in the turbine and generator general specs coordination and approval process; providing support throughout the design and engineering documentation preparation phase;
- providing support during the Design requirements specification preparation process;
- providing monitoring and support during the Basic Engineering and Design Documentation preparation phases of the abovementioned Turbine unit upgrade project.