+7 (499) 705-11-28

RENDERING SUPPORT SERVICES FOR THE SMOLENSKAYA CHP PLANT NO. 2 TURBINE UNIT NO. 3 UPGRADE PROJECT, PLANNED AS PART OF THE RUSSIA-WIDE DPM HEAT PLANTS MODERNIZATION PROGRAM

The Smolenskaya combined heat-and-power plant no. 2 is located in the town of Smolensk and is run by a company owned by the Quadra PJSC.
It delivers heat and electricity to the town of Smolensk.
Rated electric power output: 275 MW.
Rated heat output: 774 Gcal/h
EF-TEK is now providing support services for this plant´s Turbine unit No. 3 upgrade project. The scope of these services is as follows:
  • providing support during the Turbine unit no. 3 main building foundation survey;
  • participation in the long-lead equipment (turbine and generator) supply contract draft preparation; turbine and generator ToR drafting;
  • participation in the turbine and generator general specs coordination and approval process; providing support throughout the design and engineering documentation preparation phase;
  • providing support during the Design requirements specification preparation process;
  • providing monitoring and support during the Basic Engineering and Design Documentation preparation phases of the abovementioned Turbine unit upgrade project.

EF-TEK WILL BE PERFORMING TECHNOLOGY AND PRICE AUDITS OF TWO INVESTMENT PROJECTS FOR THE ROSSETI TYUMEN JSC

EF-TEK won two electronic tenders and will be doing public technology and price audits of two investment projects: Stage three of the Batovo 110/10 kV substation upgrade project (this project includes implementation of the so-called 110-13 diagram, construction of the substation control house, installation of ten 110 kV cells, as well as connecting to a 110 kV power line), and Stage four of the Erginskaya 110/35/6 kV substation construction project (this construction project covers this 110/35/6 kV substation with 2x40 MVA transformers itself, as well as the respective 2x36km high voltage power line).

EF-TEK TOOK PART IN A CONFERENCE DEDICATED TO ENCOURAGING PRIVATE INVESTMENTS IN THE DISTRIBUTED GENERATION DEVELOPMENT

April the 14th 2021 EF-TEK participated in a round table entitled “Attraction of private investments into the development of distributed power generation in remote and isolated areas of the Far East and Arctic - from conception to implementation”. This forum took place with the support of the Ministry for the Development of the Russian Far East, the Far East and Arctic Development Corporation, and the Eastern State Planning Center.

EF-TEK SIGNED A CONTRACT WITH THE SIBIRENERGOREMONT JSC

Under this contract, EF-TEK will be surveying Krasnoyarsk combined heat-and-power plant´s steam boilers to be upgraded under the so-called DPM-2 program (which is the second stage of the Russian Federal heat generation plants modernization program - Translator).

RUNNING A CONSTRUCTION INVESTMENTS FEASIBILITY STUDY FOR MOSENERGO

EF-TEK won a tender and was awarded a contract to conduct an investments feasibility study for the construction project to be implemented at the diesel engine powered emergency power unit of the Combined heat-and-power plant no. 27 belonging to a MosEnergo company branch.